Several major construction milestones have been achieved at Level.

In the East Building, framing is now complete on all levels, with roofing underway. Work is progressing with plumbing, electrical, mechanical, and fire protection systems rough-in, along with window prep and installation.

In the West Building, framing is coming up above the ground and has advanced to Level 2.

In the parkade, installation of plumbing systems and fire sprinkler piping is moving forward steadily with sani & sewer piping ready to connect to the offsite civil.

East Building – Structural wood framing completed

Several major construction milestones have been achieved at Level. In the East Building, framing is now complete on all levels, with roofing underway. Work is progressing with plumbing, electrical, mechanical,…

Read More

Excavation is now complete!

Footings and foundation work has commenced, and below-grade waterproofing and exterior walls have started on P3. The crane has been erected to facilitate construction activities as the project progresses above…

Read More

We have officially completed excavation of our parkade.

We will begin pouring concrete in the coming weeks, followed by the structural framework later this year.

Read More